APPROVED – Valley Line West LRT Accelerated Construction
On February 11, 2025, the Edmonton City Council’s Urban Planning Committee voted 5-0 to proceed with the accelerated roadway plan described in the Valley Line West 2025 Roadway Construction Options and Impacts report.
The plan, developed by Marigold Infrastructure Partners (MIP) and the City of Edmonton, aims to accelerate 2025 roadwork construction, with the goal to reduce the overall time frame of traffic restrictions in key areas by more than half.

PHASE 1
April - July
PHASE 2
July - Sept
PHASE 3
Sept - Nov
• 104 Ave corridor
(106 Street to 121 Street)
• Stony Plain Rd & 124 St (full closure)
• Stony Plain Rd & 156 St
• 87 Ave & Meadowlark Rd
• 104 Avenue corridor
(106 Street to 121 Street)
• Stony Plain Rd & 142 St
• 95 Ave 156 St
• 104 Ave corridor
(106 Street to 121 Street)
• Stony Plain Rd & 149 St
The work has been divided into three phases to focus efforts on one major north/south arterial road at a time, leaving the next adjacent arterial road available to carry diverted traffic.
The table to the right summarizes the impacted locations within the accelerated plan, along with approximate timeframes of the accelerated plan compared to the timeframe under the Project Agreement.
Intersection
|
New timeline |
Original timeline |
Stony Plain Rd & 124 St
|
6-8 weeks |
48 weeks
|
Stony Plain Rd at 156 St |
10-12 weeks |
36 weeks |
87 Ave & Meadowlark Rd |
8-10 weeks |
24 weeks |
Stony Plain Rd at 142 St |
7-9 weeks |
24 weeks |
95 Ave & 156 St |
7-9 weeks |
36 weeks |
Stony Plain Rd at 149 St |
7-9 weeks |
24 weeks |
104 Ave (106 - 121 St)
|
28 - 36 weeks |
52 weeks
|
PDFs of the report and attachments reviewed and available here:
ATTACHMENT 1:
Proposed Traffic Restrictions
ATTACHMENT 2:
Overview of Public Communications
If you have any questions, comments, or ideas for the City of Edmonton regarding this decision and the Report, please email [email protected] or call 780-496-4874.
If you have questions, comments, or ideas for Marigold Infrastructure Partners regarding construction related to this Report, please email MIP at [email protected] or phone MIP at 780-412-2183.
The details above are subject to change. Report and attachments sourced from CoE.